Below is a list of programmed works on Southland state highways next week.
Key renewal sites in Southland currently underway/beginning:
SH1 Bluff highway – Stage two north of Clifden is likely to begin next week. Traffic lights in place, delays of 5-10 minutes.
SH93 Old Coach Road - Underway and likely to continue until mid-December. Traffic lights in place, delays of 5 -10 minutes.
SH94 at The Key - Underway and likely to continue until mid-December. Traffic lights in place, 10-15 minute delays. Team will be moving to Mararoa School end to begin stage two next week.
SH97 Mossburn-Five Rivers Highway (at Five Rivers end) – Underway and likely to be completed early the week of the 24th November. Traffic lights in place, delays of 5 -10 minutes.
SH97 Mossburn-Five Rivers Highway (near Ellis Road) – Underway and likely to continue for 2-3 weeks. Traffic lights in place, delays of 5 -10 minutes.
SH90 Waikaka Valley highway between Waikaka Road and Cunningham Road – earthworks and drainage beginning Monday 17th November until late December. Construction will begin in new year. Traffic lights in place, delays of 5-10 minutes.
Other maintenance and contractor work underway next week is listed below.
A map of all known work is mapped HERE.
Highways South maintenance work:
**Programmed work may be delayed due to weather/other factors.
Other contractor work that we are aware of:
Useful links:
NZTA Journeys website - https://www.journeys.nzta.govt.nz/journey-planner
Freight Impact Register - https://www.nzta.govt.nz/commercial-driving/trucks-and-tow-trucks/potential-restrictions-affecting-freight/ - download and filter the region for ‘Southland’. This will indicate any upcoming work in the next fortnight which have closures, detours or width restrictions for freight.